(a)Reassessment of major system If the Director of National Intelligence determines under section 3101(d) of this title that the total acquisition cost of a major system has increased by a percentage equal to or greater than the critical cost growth threshold for the major system, the Director shall—
(1)determine the root cause or causes of the critical cost growth, in accordance with applicable statutory requirements, policies, procedures, and guidance; and
(2)carry out an assessment of—
(A)the projected cost of completing the major system if current requirements are not modified;
(B)the projected cost of completing the major system based on reasonable modification of such requirements;
(C)the rough order of magnitude of the costs of any reasonable alternative system or capability;

Free access — add to your briefcase to read the full text and ask questions with AI

50 U.S.C. § 3102 (Critical cost growth in major systems) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

§ 3101
50 U.S.C. § 3101

Source Credit

History

(July 26, 1947, ch. 343, title V, §506F, as added Pub. L. 111–259, title III, §324(a), Oct. 7, 2010, 124 Stat. 2679.)

Editorial Notes

Editorial Notes

Codification
Section was formerly classified to section 415a–8 of this title prior to editorial reclassification and renumbering as this section.