Text

(a)In general On completion of an appraisal report under section 2404(c) of this title that recommends undertaking a feasibility study and subject to the availability of appropriations, the Secretary shall—
(1)in cooperation with a non-Federal project entity, carry out a study to determine the feasibility of the proposed rural water supply project;
(2)receive and review a feasibility study that is—
(A)developed by the non-Federal project entity, with or without support from the Secretary; and
(B)submitted to the Secretary by the non-Federal project entity; or
(3)(A) provide a grant to, or enter into a cooperative agreement with, a non-Federal project entity to conduct a feasibility study, for submission to the Secretary, if the Secretary determines that—
(i)the non-Federal entity is

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 2404
43 U.S.C. § 2404

Source Credit

History

(Pub. L. 109–451, title I, §106, Dec. 22, 2006, 120 Stat. 3351.)

Cite This Page — Counsel Stack

Bluebook (online)
43 U.S.C. § 2405, Counsel Stack Legal Research, https://law.counselstack.com/usc/43/2405.