FEDERAL · 42 U.S.C. · Chapter SUBCHAPTER II—NEW FACILITIES

Permanent exemptions

42 U.S.C. § 8322
Title42The Public Health and Welfare
ChapterSUBCHAPTER II—NEW FACILITIES
PartB

This text of 42 U.S.C. § 8322 (Permanent exemptions) is published on Counsel Stack Legal Research, covering United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
42 U.S.C. § 8322.

Text

(a)Permanent exemption due to lack of alternate fuel supply, site limitations, environmental requirements, or adequate capital
(1)After consideration of a petition (and comments thereon) for an exemption for a powerplant from the prohibitions of part A, the Secretary shall, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum, if he finds that the petitioner has demonstrated that despite diligent good faith efforts—
(A)it is likely that an adequate and reliable supply of coal or other alternate fuel of the quality necessary to conform with design and operational requirements for use as a primary energy source (i) will not be available within the first 10 years of the useful life of the powerplant, or (ii) will not be available at a cost (t

Free access — add to your briefcase to read the full text and ask questions with AI

Source Credit

History

(Pub. L. 95–620, title II, §212, Nov. 9, 1978, 92 Stat. 3300; Pub. L. 100–42, §1(c)(6), May 21, 1987, 101 Stat. 312.)

Editorial Notes

Editorial Notes

References in Text
This chapter, referred to in subsec. (b)(3), was in the original "this Act", meaning Pub. L. 95–620, Nov. 9, 1978, 92 Stat. 3289, known as the Powerplant and Industrial Fuel Use Act of 1978, which is classified principally to this chapter. For complete classification of this Act to the Code, see Short Title note set out under section 8301 of this title and Tables.

Amendments
1987—Subsec. (a)(1). Pub. L. 100–42, §1(c)(6)(A)–(C), substituted "from" for "or installation from one or more of" in introductory provisions, substituted "the fuel that would be used" for "using imported petroleum" and struck out "or installation" after "powerplant" wherever appearing in subpar. (A), and struck out "or installation" after "powerplant" in subpars. (B) and (D).
Subsec. (a)(2). Pub. L. 100–42, §1(c)(1)(D), struck out "—
"(A) in the case of a new major fuel-burning installation, be made with respect to the site of such installation proposed by the petitioner; and
"(B) in the case of a new electric powerplant,"
after "paragraph (1) shall".
Subsec. (a)(3). Pub. L. 100–42, §1(c)(6)(E), struck out par. (3) which read as follows: "Notwithstanding the preceding provisions of this subsection, a powerplant which has been granted an exemption under subsection (h) may not be granted an exemption under this subsection."
Subsec. (b). Pub. L. 100–42, §1(c)(6)(A), (B), (F), in introductory provisions substituted "from" for "or installation from one or more of", in par. (1) struck out "or installation" after "powerplant", and in par. (2) struck out "in the case of a powerplant," after "(2)".
Subsec. (d). Pub. L. 100–42, §1(c)(6)(A), (B), (G), struck out "(1)" before "After consideration of", substituted "from" for "installation from one or more of" in introductory provisions, redesignated subpars. (A) and (B) of former par. (1) as pars. (1) and (2), respectively, struck out "or installation" after "powerplant" wherever appearing in such pars., and struck out former par. (2) which read as follows: "In the case of a new major fuel-burning installation, the percentage determined by the Secretary under subparagraph (B) of paragraph (1) shall not be less than 25 percent."
Subsec. (e). Pub. L. 100–42, §1(c)(6)(B), struck out "or installation" after "powerplant" wherever appearing.
Subsec. (g). Pub. L. 100–42, §1(c)(6)(H), struck out subsec. (g) which related to issuance, by order of Secretary of Energy, of permanent exemptions for use of natural gas or petroleum for peakload powerplants.
Subsec. (h). Pub. L. 100–42, §1(c)(6)(H), struck out subsec. (h) which related to issuance, by order of Secretary of Energy, of permanent exemptions for use of petroleum for intermediate load powerplants.
Subsec. (i). Pub. L. 100–42, §1(c)(6)(H), struck out subsec. (i) which related to issuance, by order of Secretary of Energy, of permanent exemptions for use of natural gas or petroleum for installations based upon product or process requirements.
Subsec. (j). Pub. L. 100–42, §1(c)(6)(H), struck out subsec. (j) which related to issuance, by order of Secretary of Energy, of permanent exemptions for use of natural gas or petroleum for installations necessary to meet scheduled equipment outages.

Statutory Notes and Related Subsidiaries

Exemption for Certain Electric Powerplants as Effective Prior to 180 Days After November 9, 1978
For effectiveness of exemption for certain electric powerplants as prior to 180 days after Nov. 9, 1978, see section 902(a) of Pub. L. 95–620, set out as a note under section 8301 of this title.

Cite This Page — Counsel Stack

Bluebook (online)
42 U.S.C. § 8322, Counsel Stack Legal Research, https://law.counselstack.com/usc/42/8322.