FEDERAL · 33 U.S.C. · Chapter 12

Protection, alteration, reconstruction, relocation, or replacement of structures and facilities; contract standards; reasonable costs

Current through Pub. L. 119-102
Title 33Navigation and Navigable Waters·Ch. 12 — RIVER AND HARBOR IMPROVEMENTS GENERALLY·Subch. V
Whenever, during the construction or reconstruction of any navigation, flood control, or related water development project under the direction of the Secretary of the Army, the Chief of Engineers determines that any structure or facility owned by an agency of government and utilized in the performance of a governmental function should be protected, altered, reconstructed, relocated, or replaced to meet the requirements of navigation or flood control, or both; or to preserve the safety or integrity of such facility when its safety or usefulness is determined by the Chief of Engineers to be adversely affected or threatened by the project, the Chief of Engineers may, if he deems such action to be in the public interest, enter into a contract providing for (1) the payment from appropriations m

Free access — add to your briefcase to read the full text and ask questions with AI

33 U.S.C. § 633 (Protection, alteration, reconstruction, relocation, or replacement of structures and facilities; contract standards; reasonable costs) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Source Credit

History

(Pub. L. 85–500, title I, §111, July 3, 1958, 72 Stat. 303; Pub. L. 89–298, title III, §309, Oct. 27, 1965, 79 Stat. 1094.)

Editorial Notes

Editorial Notes

Amendments
1965—Pub. L. 89–298 provided for payment of the reasonable cost of replacing, relocating, or reconstructing the facility to a reasonable standard, not exceeding minimum standard of State or political subdivision for same type of facility involved, except that if the existing facility exceeds the minimum standard of the State or political subdivision, the Chief of Engineers may provide a facility of comparable standard, in provision designated as clause (1), eliminated former provision for payment of reasonable actual cost of the remedial work, and designated existing provisions as clause (2).