Determination of project completion
Current through Pub. L. 119-102
(a)In general
The Secretary shall notify the applicable non-Federal interest when construction of a water resources project or a functional portion of the project is completed so the non-Federal interest may commence responsibilities, as applicable, for operating and maintaining the project.
(b)Non-Federal interest appeal of determination
(1)In general
Not later than 7 days after receiving a notification under subsection (a), the non-Federal interest may appeal the completion determination of the Secretary in writing with a detailed explanation of the basis for questioning the completeness of the project or functional portion of the project.
(2)Independent review
(A)In general
On notification that a non-Federal interest has submitted an appeal under paragraph (1), the Secretary shall
Free access — add to your briefcase to read the full text and ask questions with AI
33 U.S.C. § 2347a (Determination of project completion) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Source Credit
History
(Pub. L. 113–121, title I, §1010, June 10, 2014, 128 Stat. 1217.)
Editorial Notes
Editorial Notes
Codification
Section was enacted as part of the Water Resources Reform and Development Act of 2014, and not as part of the Water Resources Development Act of 1986 which comprises this chapter.
Statutory Notes and Related Subsidiaries
"Secretary" Defined
Secretary means the Secretary of the Army, see section 2 of Pub. L. 113–121, set out as a note under section 2201 of this title.
Codification
Section was enacted as part of the Water Resources Reform and Development Act of 2014, and not as part of the Water Resources Development Act of 1986 which comprises this chapter.
Statutory Notes and Related Subsidiaries
"Secretary" Defined
Secretary means the Secretary of the Army, see section 2 of Pub. L. 113–121, set out as a note under section 2201 of this title.