FEDERAL · 10 U.S.C. · Chapter 607
Matters relating to critical decisions
Current through Pub. L. 119-102
(a)Post-critical Decision 2 Changes.—After the date on which a plant project specifically authorized by law and carried out under Department of Energy Order 413.3B (relating to program management and project management for the acquisition of capital assets), or a successor order, achieves critical decision 2, the Administrator may not change the requirements for such project if such change increases the cost of such project by more than the lesser of $5,000,000 or 15 percent, unless—
(1)the Administrator submits to the congressional defense committees—
(A)a certification that the Administrator, without delegation, authorizes such proposed change; and
(B)a cost-benefit and risk analysis of such proposed change, including with respect to—
(i)the effects of such proposed change on the pr
Free access — add to your briefcase to read the full text and ask questions with AI
10 U.S.C. § 6287 (Matters relating to critical decisions) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Source Credit
History
(Added Pub. L. 119–60, div. C, title XXXI, §3111(a), Dec. 18, 2025, 139 Stat. 1435.)
Editorial Notes
Editorial Notes
Prior Provisions
Provisions similar to those in this section were contained in section 2755 of Title 50, War and National Defense, prior to repeal by Pub. L. 119–60, §3111(b)(1).
Prior Provisions
Provisions similar to those in this section were contained in section 2755 of Title 50, War and National Defense, prior to repeal by Pub. L. 119–60, §3111(b)(1).