§ 36-7-321 — Terms

Wyoming § 36-7-321
JurisdictionWyoming
Title 36Public Land
Ch. 7CAREY ACT LANDS
Art. 3RECLAMATION OF LAND

This text of Wyoming § 36-7-321 (Terms) is published on Counsel Stack Legal Research, covering Wyoming primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wyo. Stat. Ann. § 36-7-321 (2026).

Text

No contract shall be made by the board which requires a greater time than five (5) years for the construction of the canal, works or irrigation system, and all contracts shall be conditioned that active construction work shall begin within six

(6)months from the date of the contract, and that at least one-tenth of the construction work shall be completed within one
(1)year of the date of the contract; that at least one-third of the construction work shall be completed within two (2) years from the date of the contract, and that construction shall be prosecuted diligently and continuously to completion; and that a cessation of work under the contract with the state for a period of ninety (90) days during the months of May, June, July, August, September, October and November, after the sec

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Wyoming § 36-7-321, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/7/36-7-321.