(a)A public entity awarding a contract for a public work shall authorize partial payments of the amount due under the contract as stipulated in the contract document or as soon thereafter as practicable, to the contractor if the contractor is satisfactorily performing the contract.
(b)In all contracts with a public entity for a public work, the public entity may retain no more than five percent (5%) of the calculated value of any work completed as retainage. The retained payment shall be due and payable as prescribed by W.S. 16-6-116(a). The retained payment shall be held in an account in the name of the contractor which account has been assigned to the public entity. If the public entity finds that satisfactory progress is being made in all phases of the contract it may, upon written re

Free access — add to your briefcase to read the full text and ask questions with AI

Wyoming § 16-6-702 (Public entity; contracts; partial payments; retainage; alternate delivery methods authorized) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

15
View on official source ↗