This text of Wyoming § 16-6-702 (Public entity; contracts; partial payments; retainage; alternate delivery methods authorized) is published on Counsel Stack Legal Research, covering Wyoming primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Wyo. Stat. Ann. § 16-6-702 (2026).
Text
(a)A public entity awarding a contract for a public work
shall authorize partial payments of the amount due under the
contract as stipulated in the contract document or as soon
thereafter as practicable, to the contractor if the contractor
is satisfactorily performing the contract.
(b)In all contracts with a public entity for a public
work, the public entity may retain no more than five percent
(5%) of the calculated value of any work completed as retainage.
The retained payment shall be due and payable as prescribed by
W.S. 16-6-116(a). The retained payment shall be held in an
account in the name of the contractor which account has been
assigned to the public entity. If the public entity finds that
satisfactory progress is being made in all phases of the
contract it may, upon written re
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 16-6-101
DefinitionsCite This Page — Counsel Stack
Bluebook (online)
Wyoming § 16-6-702, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/6/16-6-702.