§ 16-6-121 — Notice required to receive protection under a bond or guarantee; limitation; notice required by owner in project specifications
Wyoming·Title 16 City, County, State and Local Powers·Ch. 6 PUBLIC PROPERTY·Art. 1 PUBLIC WORKS AND CONTRACTS
(a)Any subcontractor or materialman entitled to the
protection of a bond or other form of guarantee approved by a
public entity under W.S. 16-6-112 shall give notice of his right
to that protection to the general contractor. Failure to give
notice to a general contractor who has complied with subsections
(f)and (g) of this section waives the subcontractor or
materialman's protection under the bond or guarantee.
(b)The notice shall be given no later than sixty (60)
days after the date on which services or materials are first
furnished.
(c)The notice shall be sent to the general contractor by
certified mail, electronic means or delivered to and receipted
by the general contractor or his agent. Notice by certified
mail or electronic means is effective on the date the notice is
mailed or s
Free access — add to your briefcase to read the full text and ask questions with AI
Wyoming § 16-6-121 (Notice required to receive protection under a bond or guarantee; limitation; notice required by owner in project specifications) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Nearby Sections
15
§ 16-6-101
Definitions