§ 29-2-112 — Preliminary notices

Wyoming·Title 29 Liens·Ch. 2 CONTRACTORS OR MATERIALMEN
(a)With respect to perfecting the right to file a construction lien under this chapter, the following preliminary notice requirements shall apply:
(i)The contractor, subcontractor and materialman shall send written notice to the record owner or his agent, of the right to assert a lien against the property for which services or materials are provided if the contractor, subcontractor or materialman is not paid, and the right of the owner or contractor to obtain a lien waiver upon payment for services or materials. Each subcontractor and materialman shall provide a copy of the written notice to the contractor for which the subcontractor or materialman is providing services or materials;
(ii)Any notice required under this section shall be sent:
(A)By the contractor prior to receiving any p

Free access — add to your briefcase to read the full text and ask questions with AI

Wyoming § 29-2-112 (Preliminary notices) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

13
View on official source ↗