§ 8A-13-2 — Deadline

West Virginia·Ch. 8A LAND USE PLANNING·Art. 13 LOCAL PERMITTING DEADLINES
(a)If an applicant submits a request to a governing body or planning commission of a municipality or county, then the governing body or planning commission of the municipality or county must approve or deny the applicant's request within 60 days. The following applies if:
(1)The governing body or planning commission fails to approve or deny the applicant's request within 60 days, then the request is approved.
(2)The time limit in this section begins upon the governing body or planning commission's receipt of a request from an applicant.
(3)The governing body or planning commission approves the request, then the governing body or planning commission may not impose on the applicant additional requirements related to the request.
(4)The governing body or planning commission denies th

Free access — add to your briefcase to read the full text and ask questions with AI

West Virginia § 8A-13-2 (Deadline) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

2024 Reg. Sess., SB782; 2007 Reg. Sess., SB368

Nearby Sections

15
View on official source ↗