W. Va. Code § 5-22-4 (2026).

Text

(a)The state and its subdivisions may establish a maximum budgeted amount for each construction project. In the event the bids for a construction project exceed the funds available, the contracting public agency may negotiate with the lowest qualified responsible bidder pursuant to the provisions of this section.
(b)To utilize the provisions of this section, the contracting public agency shall:
(1)Establish a maximum budgeted amount;
(2)Maintain confidentiality of the maximum budgeted amount prior to the award of a contract; and
(3)Not proceed with a negotiated award if that results in more than a 10 percent change in cost from the original base bid.
(c)A negotiated award made pursuant to the provisions of this section shall be made within 60 calendar days of the original bid op

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

2025 Reg. Sess., SB587; 2024 Reg. Sess., SB156; 2024 Reg. Sess., SB217; 2023 Reg. Sess., SB21; 2023 Reg. Sess., SB539; 2021 Reg. Sess., SB370; 2018 Reg. Sess., SB474; 2017 Reg. Sess., SB412; 2014 Reg. Sess., HB4168

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
West Virginia § 5-22-4, Counsel Stack Legal Research, https://law.counselstack.com/statute/wv/5/5-22-4.