§ 5-22-4 — Negotiation when all bids exceed budgeted amount
West Virginia·Ch. 5 GENERAL POWERS AND AUTHORITY OF THE GOVERNOR, SECRETARY OF STATE AND ATTORNEY GENERAL; BOARD OF PUBLIC WORKS; MISCELLANEOUS AGENCIES, COMMISSIONS, OFFICES, PROGRAMS, ETC·Art. 22 GOVERNMENT CONSTRUCTION CONTRACTS
(a)The state and its subdivisions may establish a maximum budgeted amount for each construction project. In the event the bids for a construction project exceed the funds available, the contracting public agency may negotiate with the lowest qualified responsible bidder pursuant to the provisions of this section.
(b)To utilize the provisions of this section, the contracting public agency shall:
(1)Establish a maximum budgeted amount;
(2)Maintain confidentiality of the maximum budgeted amount prior to the award of a contract; and
(3)Not proceed with a negotiated award if that results in more than a 10 percent change in cost from the original base bid.
(c)A negotiated award made pursuant to the provisions of this section shall be made within 60 calendar days of the original bid op
Free access — add to your briefcase to read the full text and ask questions with AI
West Virginia § 5-22-4 (Negotiation when all bids exceed budgeted amount) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
2025 Reg. Sess., SB587; 2024 Reg. Sess., SB156; 2024 Reg. Sess., SB217; 2023 Reg. Sess., SB21; 2023 Reg. Sess., SB539; 2021 Reg. Sess., SB370; 2018 Reg. Sess., SB474; 2017 Reg. Sess., SB412; 2014 Reg. Sess., HB4168