West Virginia Statutes

§ 21-11A-12 — Timetable

West Virginia § 21-11A-12
JurisdictionWest Virginia
Ch. 21LABOR
Art. 11ANOTICE AND OPPORTUNITY TO CURE CONSTRUCTION DEFECTS

This text of West Virginia § 21-11A-12 (Timetable) is published on Counsel Stack Legal Research, covering West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. Va. Code § 21-11A-12 (2026).

Text

(a)Following receipt of a claimant's notice of claim, the contractor or other designated representative shall review the claimant's claim and initiate negotiations with the claimant to attempt to resolve the claim.
(b)Subject to subsection (c) of this section, the parties shall begin negotiations within a reasonable period of time not to exceed thirty days following the date the contractor receives the claimant's notice of claim.
(c)The parties may conduct negotiations according to an agreed schedule, but must begin negotiations no later than the deadline set forth in subsection (b) of this section.
(d)Subject to subsection (e) of this section, the parties shall complete the negotiations that are required by this article within ninety days after the contractor receives the claimant'

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

2003 Reg. Sess., SB440

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
West Virginia § 21-11A-12, Counsel Stack Legal Research, https://law.counselstack.com/statute/wv/21/21-11A-12.