Wisconsin Statutes
§ 893.59 — Actions concerning damage to highway or railroad grade.
Wisconsin § 893.59
JurisdictionWisconsin
Ch. 893Limitations of commencement of actions and proceedings; procedure for claims against governmental units
Subch.subch. V of ch. 893 SUBCHAPTER V
TORT ACTIONS
This text of Wisconsin § 893.59 (Actions concerning damage to highway or railroad grade.) is published on Counsel Stack Legal Research, covering Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Wis. Stat. § 893.59 (2026).
Text
893.59 An action under s. 88.87 (3) (b) to recover damages to a highway or railroad grade shall be commenced within 90 days after the alleged damage occurred or be barred.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
893.59 History History: 1979 c. 323 .
Nearby Sections
15
§ 893.02
Action, when commenced.§ 893.03
Presenting claims.§ 893.10
Actions, time for commencing.§ 893.16
Person under disability.Cite This Page — Counsel Stack
Bluebook (online)
Wisconsin § 893.59, Counsel Stack Legal Research, https://law.counselstack.com/statute/wi/893.59.