Washington Statutes

§ 80.54.040 — Criteria for just and reasonable rate.

Washington § 80.54.040
JurisdictionWashington
Title 80PUBLIC UTILITIES
Ch. 80.54ATTACHMENTS TO TRANSMISSION FACILITIES

This text of Washington § 80.54.040 (Criteria for just and reasonable rate.) is published on Counsel Stack Legal Research, covering Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wash. Rev. Code § 80.54.040 (2026).

Text

A just and reasonable rate shall assure the utility the recovery of not less than all the additional costs of procuring and maintaining pole attachments, nor more than the actual capital and operating expenses, including just compensation, of the utility attributable to that portion of the pole, duct, or conduit used for the pole attachment, including a share of the required support and clearance space, in proportion to the space used for the pole attachment, as compared to all other uses made of the subject facilities, and uses which remain available to the owner or owners of the subject facilities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pub. Util. Dist. No. 2 of Pac. Cnty., Mun. Corp. v. Comcast of Wash. Iv, Inc.
438 P.3d 1212 (Court of Appeals of Washington, 2019)
10 case citations
Pud No. 2 Of Pacific County v. Comcast And Centurytel
(Court of Appeals of Washington, 2019)

Legislative History

[1979 c 33 s 4.]

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Washington § 80.54.040, Counsel Stack Legal Research, https://law.counselstack.com/statute/wa/80.54.040.