§ 64.55.110 — Case schedule plan—Deadlines.

Washington § 64.55.110
JurisdictionWashington
Title 64REAL PROPERTY AND CONVEYANCES
Ch. 64.55CONSTRUCTION DEFECT DISPUTES—MULTIUNIT RESIDENTIAL BUILDINGS

This text of Washington § 64.55.110 (Case schedule plan—Deadlines.) is published on Counsel Stack Legal Research, covering Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wash. Rev. Code § 64.55.110 (2026).

Text

(1)Not less than sixty days after the later of filing or service of the complaint, the parties shall confer to create a proposed case schedule plan for submission to the court that includes the following deadlines:
(a)Selection of a mediator;
(b)Commencement of the mandatory mediation and submission of mediation materials required by this chapter;
(c)Selection of the arbitrator by the parties, where applicable;
(d)Joinder of additional parties in the action;
(e)Completion of each party's investigation;
(f)Disclosure of each party's proposed repair plan;
(g)Disclosure of each party's estimated costs of repair;
(h)Meeting of parties and experts to confer in accordance with RCW 64.55.120 ; and
(i)Disclosure of each party's settlement demand or response.
(2)If the parties

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Satomi Owners Ass'n v. Satomi, LLC
225 P.3d 213 (Washington Supreme Court, 2009)
125 case citations

Legislative History

[2005 c 456 s 12.]

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Washington § 64.55.110, Counsel Stack Legal Research, https://law.counselstack.com/statute/wa/64.55.110.