§ 60.30.010 — Retainage.
Washington § 60.30.010
This text of Washington § 60.30.010 (Retainage.) is published on Counsel Stack Legal Research, covering Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Wash. Rev. Code § 60.30.010 (2026).
Text
(1)An owner, contractor, subcontractor, or supplier may withhold as retainage an amount equal to not more than five percent of the contract price of the work completed for private construction projects. Partial payment allowed under this subsection is not acceptance or approval of some of the work or a waiver of defects in the work.
(2)The owner, contractor, subcontractor, or supplier shall pay interest at the rate of one percent per month on the final payment due the contractor, subcontractor, or supplier. The interest shall commence 30 days after the contractor, subcontractor, or supplier has completed and the owner has accepted the work under the contract for construction for which the final payment is due. The interest shall run until the date when final payment is tendered to the c
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
[2024 c 101 s 1;2023 c 373 s 1.]
Nearby Sections
15
§ 60.04.011
Definitions.§ 60.04.021
Lien authorized.§ 60.04.031
Notices—Exceptions.§ 60.04.041
Contractor registration.§ 60.04.051
Property subject to lien.§ 60.04.061
Priority of lien.§ 60.04.071
Release of lien rights.§ 60.04.081
Frivolous claim—Procedure.§ 60.04.091
Recording—Time—Contents of lien.§ 60.04.101
Separate residential units—Time for filing.§ 60.04.111
Recording—Fees.§ 60.04.121
Lien—Assignment.§ 60.04.131
Claims—Designation of amount due.§ 60.04.141
Lien—Duration—Procedural limitations.Cite This Page — Counsel Stack
Bluebook (online)
Washington § 60.30.010, Counsel Stack Legal Research, https://law.counselstack.com/statute/wa/60.30.010.