§ 60.28.080 — Delay due to litigation—Change order or force account directive—Costs—Arbitration—Termination.

Washington § 60.28.080
JurisdictionWashington
Title 60LIENS
Ch. 60.28LIEN FOR LABOR, MATERIALS, TAXES ON PUBLIC WORKS

This text of Washington § 60.28.080 (Delay due to litigation—Change order or force account directive—Costs—Arbitration—Termination.) is published on Counsel Stack Legal Research, covering Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wash. Rev. Code § 60.28.080 (2026).

Text

(1)If any delay in issuance of notice to proceed or in construction following an award of any public construction contract is primarily caused by acts or omissions of persons or agencies other than the contractor and a preliminary, special or permanent restraining order of a court of competent jurisdiction is issued pursuant to litigation and the appropriate public contracting body does not elect to delete the completion of the contract as provided by RCW 60.28.011 (7), the appropriate contracting body will issue a change order or force account directive to cover reasonable costs incurred by the contractor as a result of such delay. These costs shall include but not be limited to contractor's costs for wages, labor costs other than wages, wage taxes, materials, equipment rentals, insuranc

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 60.28.011
Washington § 60.28.011
§ 39.04.120
Washington § 39.04.120

Legislative History

[2009 c 219 s 8;1982 c 170 s 3;1973 1st ex.s. c 62 s 3.]