Washington Statutes

§ 60.04.221 — Notice to lender—Withholding of funds.

Washington § 60.04.221
JurisdictionWashington
Title 60LIENS
Ch. 60.04MECHANICS' AND MATERIALMEN'S LIENS

This text of Washington § 60.04.221 (Notice to lender—Withholding of funds.) is published on Counsel Stack Legal Research, covering Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wash. Rev. Code § 60.04.221 (2026).

Text

Any lender providing interim or construction financing where there is not a payment bond of at least fifty percent of the amount of construction financing shall observe the following procedures and the rights and liabilities of the lender and potential lien claimant shall be affected as follows:

(1)Any potential lien claimant who has not received a payment within five days after the date required by their contract, invoice, employee benefit plan agreement, or purchase order may within thirty-five days of the date required for payment of the contract, invoice, employee benefit plan agreement, or purchase order, give a notice as provided in subsections (2) and (3) of this section of the sums due and to become due, for which a potential lien claimant may claim a lien under this chapter. (2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Louisiana-Pacific Corp. v. Asarco Inc.
934 P.2d 685 (Washington Supreme Court, 1997)
18 case citations
Pacific Continental Bank v. Soundview 90, LLC
273 P.3d 1009 (Court of Appeals of Washington, 2012)
5 case citations
Emerald City Electric & Lighting, Inc. v. Jensen Electric, Inc.
846 P.2d 559 (Court of Appeals of Washington, 1993)
2 case citations

Legislative History

[1992 c 126 s 13;1991 c 281 s 22.]

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Washington § 60.04.221, Counsel Stack Legal Research, https://law.counselstack.com/statute/wa/60.04.221.