This text of Washington § 39.10.370 (General contractor/construction manager procedure—Maximum allowable construction cost.) is published on Counsel Stack Legal Research, covering Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wash. Rev. Code § 39.10.370 (2026).

Text

(1)The maximum allowable construction cost shall be used to establish a total contract cost for which the general contractor/construction manager shall provide a performance and payment bond. The maximum allowable construction cost shall be negotiated between the public body and the selected firm when the construction documents and specifications are at least ninety percent complete.
(2)Major bid packages may be bid in accordance with RCW 39.10.380 before agreement on the maximum allowable construction cost between the public body and the selected general contractor/construction manager. The general contractor/construction manager may issue an intent to award to the responsible bidder submitting the lowest responsive bid.
(3)The public body may, at its option, authorize the general co

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 39.10.380
Washington § 39.10.380
§ 39.10.210
Washington § 39.10.210

Legislative History

[2021 c 230 s 10;2014 c 42 s 6;2007 c 494 s 304.]

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Washington § 39.10.370, Counsel Stack Legal Research, https://law.counselstack.com/statute/wa/39.10.370.