§ 39.10.320 — Design-build procedure—Project management and contracting requirements.

Washington § 39.10.320
JurisdictionWashington
Title 39PUBLIC CONTRACTS AND INDEBTEDNESS
Ch. 39.10ALTERNATIVE PUBLIC WORKS CONTRACTING PROCEDURES

This text of Washington § 39.10.320 (Design-build procedure—Project management and contracting requirements.) is published on Counsel Stack Legal Research, covering Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wash. Rev. Code § 39.10.320 (2026).

Text

(1)A public body utilizing the design-build contracting procedure shall provide:
(a)Reasonable budget contingencies totaling not less than five percent of the anticipated contract value;
(b)Staff or consultants with expertise and prior experience in the management of comparable projects;
(c)Contract documents that include alternative dispute resolution procedures to be attempted prior to the initiation of litigation;
(d)Submission of project information, as required by the board;
(e)Contract documents that require the contractor, subcontractors, and designers to submit project information required by the board; and
(f)Contract documents that require the design builder to submit plans for inclusion of underutilized firms as subcontractors and suppliers including, but not limite

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 39.10.210
Washington § 39.10.210

Legislative History

[2019 c 212 s 5;2013 c 222 s 10;2007 c 494 s 203;1994 c 132 s 7. Formerly RCW39.10.070.]