Virginia Statutes

§ 43-8 — Sufficiency of memorandum, affidavit and notice required by § 43-7

Virginia § 43-8
JurisdictionVirginia
Title 43Mechanics' and Certain Other Liens
Ch. 1Mechanics' and Materialmen's Liens

This text of Virginia § 43-8 (Sufficiency of memorandum, affidavit and notice required by § 43-7) is published on Counsel Stack Legal Research, covering Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Va. Code Ann. § 43-8 (2026).

Text

The memorandum, affidavit and notice required by § 43-7 shall be sufficient if substantially in form and effect as follows: Memorandum for Mechanic's Lien Claimed by Subcontractor. Name of owner: ___________________________________________________________________________ Address of owner: ___________________________________________________________________________ Name of general contractor (if any): ___________________________________________________________________________ Name of claimant: ___________________________________________________________________________ Address of claimant: ___________________________________________________________________________ Contractor license or certificate number of claimant (if applicable): ____________________________________________________

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Code 1919, § 6428; 1968, c. 568; 2007, c. 504; 2013, c. 293; 2019, c. 243.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Virginia § 43-8, Counsel Stack Legal Research, https://law.counselstack.com/statute/va/43/43-8.