Utah Statutes
§ 63G-6a-1207 — Certification of change order.
Utah·Title 63G General Government·Ch. 63G-6a Utah Procurement Code·Part 63G-6a-12 Contracts and Change Orders
(1)Under a construction contract, a change order that increases the contract amount may not be made without prior written certification that the change order is within the determined project or contract budget by:
(1)(a) the fiscal officer of the entity responsible for funding the project or contract; or
(1)(b) the official responsible for monitoring and reporting upon the status of the costs of the total project or contract budget.
(2)If a change order will result in an increase in the total project or contract budget, the change order may not be made, unless:
(2)(a) sufficient funds are added to the project contract or budget; or
(2)(b) the scope of the project or contract is adjusted to permit the degree of completion feasible within the total project or contract budget as it existe
Free access — add to your briefcase to read the full text and ask questions with AI
Utah § 63G-6a-1207 (Certification of change order.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
Renumbered and Amended by Chapter 347, 2012 General Session
Nearby Sections
15
§ 63G-1-1001
Living historic landmarks.§ 63G-1-1002
Living historic landmarks designated.§ 63G-1-101
Title.§ 63G-1-1101
State holy days.§ 63G-1-201
Official state language.§ 63G-1-401
Commemorative periods.§ 63G-1-601
State symbols.§ 63G-1-701
Title.§ 63G-1-702
Definitions.§ 63G-1-703
Display of POW/MIA flag.§ 63G-1-901
Year-round daylight saving time.