§ 63G-6a-1207 — Certification of change order.
Utah § 63G-6a-1207
JurisdictionUtah
Title 63GGeneral Government
Ch. 63G-6aUtah Procurement Code
Part 63G-6a-12Contracts and Change Orders
This text of Utah § 63G-6a-1207 (Certification of change order.) is published on Counsel Stack Legal Research, covering Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Utah Code Ann. § 63G-6a-1207 (2026).
Text
(1)Under a construction contract, a change order that increases the contract amount may not be made without prior written certification that the change order is within the determined project or contract budget by:
(1)(a) the fiscal officer of the entity responsible for funding the project or contract; or
(1)(b) the official responsible for monitoring and reporting upon the status of the costs of the total project or contract budget.
(2)If a change order will result in an increase in the total project or contract budget, the change order may not be made, unless:
(2)(a) sufficient funds are added to the project contract or budget; or
(2)(b) the scope of the project or contract is adjusted to permit the degree of completion feasible within the total project or contract budget as it existe
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Renumbered and Amended by Chapter 347, 2012 General Session
Nearby Sections
15
§ 63G-1-1001
Living historic landmarks.§ 63G-1-1002
Living historic landmarks designated.§ 63G-1-101
Title.§ 63G-1-1101
State holy days.§ 63G-1-201
Official state language.§ 63G-1-401
Commemorative periods.§ 63G-1-601
State symbols.§ 63G-1-701
Title.§ 63G-1-702
Definitions.§ 63G-1-703
Display of POW/MIA flag.§ 63G-1-901
Year-round daylight saving time.Cite This Page — Counsel Stack
Bluebook (online)
Utah § 63G-6a-1207, Counsel Stack Legal Research, https://law.counselstack.com/statute/ut/63G-6a-1207.