§ 54-26-601 — Large load customer requirements -- Cost allocation.

Utah·Title 54 Public Utilities·Ch. 54-26 Large-Scale Electric Service Requirements·Part 54-26-6 Customer Requirements and Accounting

A large load customer shall pay all just and reasonable large load incremental costs necessary to receive electric service, including the costs of:

(1)generation resources;
(2)distribution system upgrades;
(3)to the extent permitted by federal law, and, as applicable, approved by the Federal Energy Regulatory Commission:
(3)(a) transmission system improvements, including network upgrades; and
(3)(b) interconnection facilities;
(4)transmission service; and
(5)other necessary infrastructure.

Free access — add to your briefcase to read the full text and ask questions with AI

Utah § 54-26-601 ( Large load customer requirements -- Cost allocation.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Enacted by Chapter 318, 2025 General Session