§ 54-26-402 — Alternative service requirements.
Utah·Title 54 Public Utilities·Ch. 54-26 Large-Scale Electric Service Requirements·Part 54-26-4 Service Provider Obligations
(1)A large load customer may enter into a large load contract with a large-scale generation provider if:
(1)(a) a qualified electric utility fails to complete an evaluation or provide a written response within the time period specified in Section 54-26-202; or
(1)(b) the qualified electric utility and large load customer cannot agree to a large load contract within 90 days after the day on which the large load customer receives the evaluation described in Section 54-26-202, unless the qualified electric utility and the large load customer mutually agree to a longer period of time.
(2)After submitting a large-scale service request, a large load customer:
(2)(a) may negotiate a contract with one or more large-scale generation providers; and
(2)(b) may not execute a contract with a large-sc
Free access — add to your briefcase to read the full text and ask questions with AI
Utah § 54-26-402 (Alternative service requirements.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
Enacted by Chapter 318, 2025 General Session
Nearby Sections
15
§ 54-1-12
Deposit of funds.§ 54-1-2
Powers and duties.§ 54-1-2.1
Alignment with state energy policy.§ 54-1-2.5
Procedures -- Adjudicative proceedings.§ 54-1-4
Official seal.§ 54-1-5
Office and office hours.