§ 54-18-301 — Notice of intent to file -- Content -- Prefiling procedures.

Utah·Title 54 Public Utilities·Ch. 54-18 Siting of High Voltage Power Line Act·Part 54-18-3 Notification - Process for Obtaining Land Use Permit - Appeal
(1)If a public utility conducts any field work in preparation of establishing a target study area before a notice of intent is filed in accordance with Subsection (2)(a), the public utility shall first notify the local land use authority of the public utility's work.
(2)(2)(a) At least 90 days before the day on which a public utility files a land use application in a city or county that requires a permit for the construction of a high voltage power line or an upgraded high voltage power line, the public utility shall submit a notice of intent to the land use authority of each affected entity.
(2)(b) The notice of intent described in Subsection (2)(a) shall include:
(2)(b)(i) the name and mailing address of the public utility, including:
(2)(b)(i)(A) the name of a contact person; and
(2)

Free access — add to your briefcase to read the full text and ask questions with AI

Utah § 54-18-301 (Notice of intent to file -- Content -- Prefiling procedures.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Enacted by Chapter 316, 2009 General Session