§ 54-18-201 — Public utility to obtain approval for high voltage power lines.

Utah·Title 54 Public Utilities·Ch. 54-18 Siting of High Voltage Power Line Act·Part 54-18-2 Public Utility Duties for High Voltage Power Lines
(1)Except as provided in Subsections (2) and (3), a public utility shall comply with the requirements of this chapter before beginning construction or operation of:
(1)(a) a high voltage power line; or
(1)(b) an upgraded high voltage power line.
(2)A public utility is not subject to the provisions of this chapter if the public utility has on or before May 12, 2009:
(2)(a) filed an application for or obtained a certificate of convenience and necessity for a high voltage power line in accordance with the provisions of Section 54-4-25; or
(2)(b) has initiated the acquisition of right-of-way for the construction of the high voltage transmission line.
(3)A transmission line that is subject to federal permitting is not subject to the provisions of this chapter.

Free access — add to your briefcase to read the full text and ask questions with AI

Utah § 54-18-201 (Public utility to obtain approval for high voltage power lines.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Enacted by Chapter 316, 2009 General Session