§ 54-14-306 — Action required of local government following board decision.
Utah § 54-14-306
JurisdictionUtah
Title 54Public Utilities
Ch. 54-14Utility Facility Review Board Act
Part 54-14-3Utility Facility Review Board
This text of Utah § 54-14-306 (Action required of local government following board decision.) is published on Counsel Stack Legal Research, covering Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Utah Code Ann. § 54-14-306 (2026).
Text
(1)If the board decides that a facility permitted to be constructed by a local government is subject to requirements or conditions that impose an estimated excess cost but do not impair the provision of safe, reliable, and adequate service to customers of the public utility, the local government shall, within 20 days following the decision of the board, determine whether it will impose the requirement or conditions imposing an estimated excess cost or issue the permit, authorization, approval, exception, or waiver without the requirements or conditions imposing an estimated excess cost.
(2)If the board decides that a facility should be constructed that the local government has prohibited, the local government shall, within 60 days following the decision of the board, issue the permit, au
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Enacted by Chapter 197, 1997 General Session
Nearby Sections
15
§ 54-1-12
Deposit of funds.§ 54-1-2
Powers and duties.§ 54-1-2.1
Alignment with state energy policy.§ 54-1-2.5
Procedures -- Adjudicative proceedings.§ 54-1-4
Official seal.§ 54-1-5
Office and office hours.Cite This Page — Counsel Stack
Bluebook (online)
Utah § 54-14-306, Counsel Stack Legal Research, https://law.counselstack.com/statute/ut/54-14-306.