§ 54-14-306 — Action required of local government following board decision.

Utah·Title 54 Public Utilities·Ch. 54-14 Utility Facility Review Board Act·Part 54-14-3 Utility Facility Review Board
(1)If the board decides that a facility permitted to be constructed by a local government is subject to requirements or conditions that impose an estimated excess cost but do not impair the provision of safe, reliable, and adequate service to customers of the public utility, the local government shall, within 20 days following the decision of the board, determine whether it will impose the requirement or conditions imposing an estimated excess cost or issue the permit, authorization, approval, exception, or waiver without the requirements or conditions imposing an estimated excess cost.
(2)If the board decides that a facility should be constructed that the local government has prohibited, the local government shall, within 60 days following the decision of the board, issue the permit, au

Free access — add to your briefcase to read the full text and ask questions with AI

Utah § 54-14-306 (Action required of local government following board decision.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Enacted by Chapter 197, 1997 General Session