Utah Statutes

§ 54-14-202 — Public utility to provide standard cost and estimated excess cost.

Utah § 54-14-202
JurisdictionUtah
Title 54Public Utilities
Ch. 54-14Utility Facility Review Board Act
Part 54-14-2Conditions on Siting of Facilities

This text of Utah § 54-14-202 (Public utility to provide standard cost and estimated excess cost.) is published on Counsel Stack Legal Research, covering Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utah Code Ann. § 54-14-202 (2026).

Text

(1)(1)(a) A public utility shall provide the information described in Subsection (1)(b) if a local government:
(1)(a)(i) is considering imposing requirements or conditions on construction of a facility that may result in an estimated excess cost and requests that the public utility provide the estimated excess cost; or
(1)(a)(ii) recommends an alternative to the public utility's proposed high voltage transmission line corridor in accordance with the provisions of Title 54, Chapter 18, Siting of High Voltage Power Line Act.
(1)(b) Subject to Subsection (1)(a), a public utility shall provide to the local government:
(1)(b)(i) (1)(b)(i)(A) the estimated standard cost of the facility; and
(1)(b)(i)(B) the estimated excess cost of the facility if constructed in accordance with local government

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Amended by Chapter 316, 2009 General Session

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Utah § 54-14-202, Counsel Stack Legal Research, https://law.counselstack.com/statute/ut/54-14-202.