§ 38-1a-701 — Action to enforce lien -- Time for filing action -- Notice of pendency of action -- Action involving a residence.

Utah·Title 38 Liens·Ch. 38-1a Preconstruction and Construction Liens·Part 38-1a-7 Enforcement of Preconstruction and Construction Liens
(1)As used in this section:
(1)(a) "Owner" has the same meaning as defined in Section 38-11-102.
(1)(b) "Residence" has the same meaning as defined in Section 38-11-102.
(2)In order to enforce a preconstruction lien or construction lien, a claimant shall file an action to enforce the lien:
(2)(a) except as provided in Subsection (2)(b), within 180 days after the day on which the claimant files:
(2)(a)(i) a notice of preconstruction lien under Section 38-1a-402, for a preconstruction lien; or
(2)(a)(ii) a notice of construction lien under Section 38-1a-502, for a construction lien; or
(2)(b) if an owner files for protection under the bankruptcy laws of the United States before the expiration of the 180-day period under Subsection (2)(a), within 90 days after the automatic stay under the

Free access — add to your briefcase to read the full text and ask questions with AI

Utah § 38-1a-701 (Action to enforce lien -- Time for filing action -- Notice of pendency of action -- Action involving a residence.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Renumbered and Amended by Chapter 278, 2012 General Session

Nearby Sections

15
View on official source ↗