This text of Utah § 38-1a-701 (Action to enforce lien -- Time for filing action -- Notice of pendency of action -- Action involving a residence.) is published on Counsel Stack Legal Research, covering Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utah Code Ann. § 38-1a-701 (2026).

Text

(1)As used in this section:
(1)(a) "Owner" has the same meaning as defined in Section 38-11-102.
(1)(b) "Residence" has the same meaning as defined in Section 38-11-102.
(2)In order to enforce a preconstruction lien or construction lien, a claimant shall file an action to enforce the lien:
(2)(a) except as provided in Subsection (2)(b), within 180 days after the day on which the claimant files:
(2)(a)(i) a notice of preconstruction lien under Section 38-1a-402, for a preconstruction lien; or
(2)(a)(ii) a notice of construction lien under Section 38-1a-502, for a construction lien; or
(2)(b) if an owner files for protection under the bankruptcy laws of the United States before the expiration of the 180-day period under Subsection (2)(a), within 90 days after the automatic stay under the

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Renumbered and Amended by Chapter 278, 2012 General Session