§ 38-1a-506 — Notice of intent to obtain final completion.

Utah § 38-1a-506
JurisdictionUtah
Title 38Liens
Ch. 38-1aPreconstruction and Construction Liens
Part 38-1a-5Construction Lien Provisions

This text of Utah § 38-1a-506 (Notice of intent to obtain final completion.) is published on Counsel Stack Legal Research, covering Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utah Code Ann. § 38-1a-506 (2026).

Text

(1)An owner of a nonresidential construction project that is registered with the registry, or an original contractor of a commercial nonresidential construction project that is registered with the registry under Section 38-1a-501, shall file with the registry a notice of intent to obtain final completion as provided in this section if:
(1)(a) the completion of performance time under the original contract for construction work is greater than 120 days;
(1)(b) the total original construction contract price exceeds $500,000; and
(1)(c) the original contractor or owner has not obtained a payment bond in accordance with Section 14-2-1.
(2)The notice of intent described in Subsection (1) shall be filed at least 45 days before the day on which the owner or original contractor of a commercial n

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Amended by Chapter 429, 2022 General Session