Utah Statutes
§ 38-1a-405 — Preconstruction liens on equal footing.
Utah § 38-1a-405
JurisdictionUtah
Title 38Liens
Ch. 38-1aPreconstruction and Construction Liens
Part 38-1a-4Preconstruction Lien Provisions
This text of Utah § 38-1a-405 (Preconstruction liens on equal footing.) is published on Counsel Stack Legal Research, covering Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Utah Code Ann. § 38-1a-405 (2026).
Text
(1)Each preconstruction lien on a project property is on equal footing with every other preconstruction lien on the project property, regardless of:
(1)(a) when the claimant submitted the claimant's notice of preconstruction service for recording;
(1)(b) when the claimant submitted the claimant's notice of preconstruction lien for recording; or
(1)(c) when the preconstruction service related to the lien occurs.
(2)Subsection (1) does not affect the priority of a construction lender's mortgage or trust deed, as established under this chapter.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Enacted by Chapter 464, 2013 General Session
Nearby Sections
15
§ 38-10-101
Definitions.§ 38-10-103
Nonimpairment of lien attached to estate less than fee or to equitable or legal contingent interest.§ 38-10-104
Limitation of interests covered by lien.§ 38-10-106
Enforcement -- Time for -- Lis pendens -- Action for debt not affected -- Execution on an interest.§ 38-10-108
Limitation upon owner's liability.§ 38-10-110
Cancellation of lien.§ 38-10-111
Abuse of lien right -- Penalty.§ 38-10-112
Assignment of lien.§ 38-10-114
Attorney fees.Cite This Page — Counsel Stack
Bluebook (online)
Utah § 38-1a-405, Counsel Stack Legal Research, https://law.counselstack.com/statute/ut/38-1a-405.