§ 38-1a-404 — When preconstruction service considered complete.

Utah·Title 38 Liens·Ch. 38-1a Preconstruction and Construction Liens·Part 38-1a-4 Preconstruction Lien Provisions
Preconstruction service is considered complete for any project, project phase, or bid package as of the date that construction work for that project, project phase, or bid package, respectively, commences.

Free access — add to your briefcase to read the full text and ask questions with AI

Utah § 38-1a-404 (When preconstruction service considered complete.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Enacted by Chapter 278, 2012 General Session