§ 38-1a-403 — Effective time and priority of preconstruction lien -- Subordination to bona fide loan.

Utah § 38-1a-403
JurisdictionUtah
Title 38Liens
Ch. 38-1aPreconstruction and Construction Liens
Part 38-1a-4Preconstruction Lien Provisions

This text of Utah § 38-1a-403 (Effective time and priority of preconstruction lien -- Subordination to bona fide loan.) is published on Counsel Stack Legal Research, covering Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utah Code Ann. § 38-1a-403 (2026).

Text

(1)Except as otherwise provided in this chapter, a preconstruction lien:
(1)(a) relates back to and takes effect as of the time of filing of the earliest timely filed notice of preconstruction service under Section 38-1a-401 for the anticipated improvement for which the preconstruction lien is claimed; and
(1)(b) has priority over:
(1)(b)(i) any lien, mortgage, or other encumbrance that attaches after the earliest timely filed notice of preconstruction service is filed; and
(1)(b)(ii) any lien, mortgage, or other encumbrance of which the claimant had no notice and that was unrecorded at the time the earliest timely filed notice of preconstruction service is filed.
(2)A preconstruction lien is subordinate to an interest securing a bona fide loan if and to the extent that the lien covers

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Amended by Chapter 464, 2013 General Session