§ 38-1a-402 — Notice of preconstruction lien -- Requirements.

Utah·Title 38 Liens·Ch. 38-1a Preconstruction and Construction Liens·Part 38-1a-4 Preconstruction Lien Provisions
(1)Within 90 days after completing a preconstruction service for which a claimant is not paid in full, a claimant who desires to claim a preconstruction lien shall submit for recording with each applicable county recorder a notice of preconstruction lien.
(2)A claimant who fails to submit a notice of preconstruction lien as provided in Subsection (1) may not claim a preconstruction lien.
(3)(3)(a) A notice of preconstruction service lien shall include:
(3)(a)(i) the claimant's name, mailing address, and telephone number;
(3)(a)(ii) a statement that the claimant claims a preconstruction lien;
(3)(a)(iii) the date the claimant's notice of preconstruction service was filed;
(3)(a)(iv) the name of the person that employed the claimant;
(3)(a)(v) a general description of the preconstruction

Free access — add to your briefcase to read the full text and ask questions with AI

Utah § 38-1a-402 (Notice of preconstruction lien -- Requirements.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Amended by Chapter 464, 2013 General Session

Nearby Sections

15
View on official source ↗