§ 214.904 — TIME FOR ISSUANCE OF MUNICIPAL BUILDING PERMIT.

Texas § 214.904
JurisdictionTexas
Code LGLocal Government Code

This text of Texas § 214.904 (TIME FOR ISSUANCE OF MUNICIPAL BUILDING PERMIT.) is published on Counsel Stack Legal Research, covering Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tex. Local Government Code Code Ann. § 214.904 (2026).

Text

Sec. 214.904. TIME FOR ISSUANCE OF MUNICIPAL BUILDING PERMIT.

(a)This section applies only to a permit required by a municipality to erect or improve a building or other structure in the municipality or its extraterritorial jurisdiction.
(b)Not later than the 45th day after the date an application for a permit is submitted, the municipality must:
(1)grant or deny the permit;
(2)provide written notice to the applicant stating the reasons why the municipality has been unable to grant or deny the permit application; or
(3)reach a written agreement with the applicant providing for a deadline for granting or denying the permit.
(c)For a permit application for which notice is provided under Subsection (b)(2), the municipality must grant or deny the permit not later than the 30th day after

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harry Bizios v. Town of Lakewood Village, Texas
(Court of Appeals of Texas, 2015)

Legislative History

Added by Acts 2005, 79th Leg., Ch. 917 (H.B. 265 ), Sec. 1, eff. September 1, 2005.