South Dakota Statutes

§ 49-41B-5 — Notification of intent to apply for permit required before filing application--Time--Prefiling conference if applicant requests.

South Dakota·Title 49 PUBLIC UTILITIES AND CARRIERS·Ch. 49-41A ENERGY CONVERSION AND TRANSMISSION FACILITIES
A notification of intent to apply for a permit for construction of an energy conversion facility or AC/DC conversion facility shall be filed with the Public Utilities Commission at least six months before filing an application as required in § 49-41B-11 . A prefiling conference may be requested by the applicant and such request shall be granted by the commission.

Free access — add to your briefcase to read the full text and ask questions with AI

South Dakota § 49-41B-5 (Notification of intent to apply for permit required before filing application--Time--Prefiling conference if applicant requests.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Otter Tail Power Co. Ex Rel. Big Stone II
2008 SD 5 (South Dakota Supreme Court, 2008)
2 case citations

Legislative History

SL 1977, ch 390, § 5; SL 2006, ch 242, § 2.

Nearby Sections

15
View on official source ↗