§ 49-41B-5 — Notification of intent to apply for permit required before filing application--Time--Prefiling conference if applicant requests.
South Dakota § 49-41B-5
JurisdictionSouth Dakota
Title 49PUBLIC UTILITIES AND CARRIERS
Ch. 49-41AENERGY CONVERSION AND TRANSMISSION FACILITIES
This text of South Dakota § 49-41B-5 (Notification of intent to apply for permit required before filing application--Time--Prefiling conference if applicant requests.) is published on Counsel Stack Legal Research, covering South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
S.D. Codified Laws § 49-41B-5 (2026).
Text
A notification of intent to apply for a permit for construction of an energy conversion facility or AC/DC conversion facility shall be filed with the Public Utilities Commission at least six months before filing an application as required in § 49-41B-11 . A prefiling conference may be requested by the applicant and such request shall be granted by the commission.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
In Re Otter Tail Power Co. Ex Rel. Big Stone II
2008 SD 5 (South Dakota Supreme Court, 2008)
Legislative History
SL 1977, ch 390, § 5; SL 2006, ch 242, § 2.
Nearby Sections
15
§ 49-1-1
Repealed§ 49-1-10
Hearings before commission--Oaths.§ 49-1-11
Rules of commission.§ 49-1-13
Annual report to Governor--Contents.§ 49-1-13.1
Repealed§ 49-1-16
Duties of state's attorneys.§ 49-1-17
Repealed§ 49-1-19
Appeals from commission.Cite This Page — Counsel Stack
Bluebook (online)
South Dakota § 49-41B-5, Counsel Stack Legal Research, https://law.counselstack.com/statute/sd/49-41B-5.