This text of South Dakota § 49-41B-25 (Permit for wind or solar energy facility--Time for complete findings by commission--Notice of decision.) is published on Counsel Stack Legal Research, covering South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
S.D. Codified Laws § 49-41B-25 (2026).
Text
Within nine months of receipt of the initial application for a permit for the construction of a wind energy facility or solar energy facility, the commission shall make complete findings, and render a decision, regarding whether a permit should be granted, denied, or granted upon such terms, conditions, or modifications of the construction, operation, or maintenance as the commission determines are appropriate. In the decision, the commission shall find that the construction of the facility meets all requirements of this chapter. Notice of the commission's decision shall be given to the applicant and to parties to the hearing within ten days following the decision.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
SL 1977, ch 390, § 19; SL 2005, ch 250, § 3; SL 2015, ch 235, § 3; SL 2019, ch 200, § 9.
Nearby Sections
15
§ 49-1-1
Repealed§ 49-1-10
Hearings before commission--Oaths.§ 49-1-11
Rules of commission.§ 49-1-13
Annual report to Governor--Contents.§ 49-1-13.1
Repealed§ 49-1-16
Duties of state's attorneys.§ 49-1-17
Repealed§ 49-1-19
Appeals from commission.Cite This Page — Counsel Stack
Bluebook (online)
South Dakota § 49-41B-25, Counsel Stack Legal Research, https://law.counselstack.com/statute/sd/49-41B-25.