§ 49-34A-84 — Requirements for refund.

South Dakota·Title 49 PUBLIC UTILITIES AND CARRIERS·Ch. 49-32A GAS AND ELECTRIC UTILITIES REGULATION

The refund pertains only to project costs incurred and paid after July 1, 2001. The refund pertains only to project costs that were incurred and paid within thirty - six months of the approval of the application required by §§ 49-34A-80 to 49-34A-92 , inclusive. No refund may be made unless:

(1)The project costs exceed five hundred thousand dollars; and (2) The person applying for the refund obtains a permit from the secretary as set forth in § 49-34A-86 .

Free access — add to your briefcase to read the full text and ask questions with AI

South Dakota § 49-34A-84 (Requirements for refund.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

SL 2001, ch 257, § 5.