This text of South Dakota § 49-16A-92 (Notice to railroad to erect fence--Contents of notice--Time for compliance.) is published on Counsel Stack Legal Research, covering South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
S.D. Codified Laws § 49-16A-92 (2026).
Text
If the owner of a tract of land has completed his portion of the fence around the proposed inclosure, he shall give written notice of its completion to the railroad on whose road the tract is situated, by service on the railroad describing in the notice the situation of the tract and the appropriate number of acres to be inclosed and the length of the fence required along the line of the railroad to complete the proposed inclosure. The railroad shall supply the materials needed to construct and complete its portion of the fence within forty - five days after the service of the notice.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
SDC 1939, § 52.0911; SDCL, § 49-20-23; SL 1976, ch 294, § 25; SL 1980, ch 322, § 91.
Nearby Sections
15
§ 49-1-1
Repealed§ 49-1-10
Hearings before commission--Oaths.§ 49-1-11
Rules of commission.§ 49-1-13
Annual report to Governor--Contents.§ 49-1-13.1
Repealed§ 49-1-16
Duties of state's attorneys.§ 49-1-17
Repealed§ 49-1-19
Appeals from commission.Cite This Page — Counsel Stack
Bluebook (online)
South Dakota § 49-16A-92, Counsel Stack Legal Research, https://law.counselstack.com/statute/sd/49-16A-92.