§ 46-4-6 — Time for construction and completion of dam.
Any person appropriating the waters of any dry - draw or watercourse within this state, within sixty days after the filing of the notice provided for in §§ 46-4-3 and 46-4-4 , shall begin the construction of the dam mentioned in § 46-4-1 for the storage or diversion of the waters, shall proceed diligently to complete the dam and shall divert the waters for beneficial use as rapidly as possible.
Free access — add to your briefcase to read the full text and ask questions with AI
South Dakota § 46-4-6 (Time for construction and completion of dam.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
SDC 1939, § 61.0133; SL 1955, ch 430, § 1; SL 1957, ch 490, § 3; SL 1959, ch 451; SDC Supp 1960, § 61.0138 (1); SL 1983, ch 318, § 7.