South Dakota Statutes

§ 46-4-6 — Time for construction and completion of dam.

South Dakota § 46-4-6
JurisdictionSouth Dakota
Title 46WATER RIGHTS
Ch. 46-4DRY-DRAW AND NONNAVIGABLE STREAM DAMS

This text of South Dakota § 46-4-6 (Time for construction and completion of dam.) is published on Counsel Stack Legal Research, covering South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.D. Codified Laws § 46-4-6 (2026).

Text

Any person appropriating the waters of any dry - draw or watercourse within this state, within sixty days after the filing of the notice provided for in §§ 46-4-3 and 46-4-4 , shall begin the construction of the dam mentioned in § 46-4-1 for the storage or diversion of the waters, shall proceed diligently to complete the dam and shall divert the waters for beneficial use as rapidly as possible.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

SDC 1939, § 61.0133; SL 1955, ch 430, § 1; SL 1957, ch 490, § 3; SL 1959, ch 451; SDC Supp 1960, § 61.0138 (1); SL 1983, ch 318, § 7.