This text of South Dakota § 1-16G-75 (Time for filing application--Contents.) is published on Counsel Stack Legal Research, covering South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Before any person receives any new frontiers payment as provided in §§ 1-16G-73 to 1-16G-84 , inclusive, the person shall file an application with GOED. The application may be filed no later than thirty days after the commencement date. No person may receive a new frontiers payment if the application is not timely filed with GOED. The application shall include the following information:
(1)The program owner's name and contact information;
(2)The general description of the program;
(3)The commencement date of the program;
(4)The projected date for completion of the program;
(5)A schedule of work for the program;
(6)The estimated program costs;
(7)The location of the program;
(8)A list of the anticipated contractors and subcontractors who will perform work on
Free access — add to your briefcase to read the full text and ask questions with AI
Before any person receives any new frontiers payment as provided in §§ 1-16G-73 to 1-16G-84 , inclusive, the person shall file an application with GOED. The application may be filed no later than thirty days after the commencement date. No person may receive a new frontiers payment if the application is not timely filed with GOED. The application shall include the following information: (1) The program owner's name and contact information; (2) The general description of the program; (3) The commencement date of the program; (4) The projected date for completion of the program; (5) A schedule of work for the program; (6) The estimated program costs; (7) The location of the program; (8) A list of the anticipated contractors and subcontractors who will perform work on the program; (9) A copy of any approval notification by a federal authority; (10) A commitment from the program owner to manufacture or process the product resulting from the program in South Dakota; and (11) Any other information that GOED may require. The application shall be on a form prescribed by the commissioner. The application shall be signed by the program owner under penalty of perjury. No application may include more than one program.