§ 58-27-460 — Promulgation of standards for interconnection of renewable energy facilities; certain generation activities prohibited.

South Carolina § 58-27-460
JurisdictionSouth Carolina
Title 58PUBLIC UTILITIES, SERVICES AND CARRIERS
Ch. 27ELECTRIC UTILITIES AND ELECTRIC COOPERATIVES

This text of South Carolina § 58-27-460 (Promulgation of standards for interconnection of renewable energy facilities; certain generation activities prohibited.) is published on Counsel Stack Legal Research, covering South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.C. Code Ann. § 58-27-460 (2026).

Text

(A)(1) The commission shall promulgate and periodically review standards for interconnection and parallel operation of generating facilities to an electrical utility's distribution and transmission system, where such interconnection is under the jurisdiction of the commission pursuant to Title 16, Chapter 12, Subchapter II of the United States Code, as amended, regulations and orders of the Federal Energy Regulatory Commission, and the laws of South Carolina. Each electrical utility shall implement such standards in a fair, nondiscriminatory manner.
(2)The commission shall, within six months of the effective date of the amendments to this section, establish proceedings for the purpose of considering revisions to the standards promulgated pursuant to this section. In developing such revisi

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

HISTORY: 2014 Act No. 236 (S.1189), SECTION 6, eff June 2, 2014; 2019 Act No. 62 (H.3659), SECTION 10, eff May 16, 2019. Editor's Note 2014 Act No. 236, SECTION 9, provides as follows: "SECTION 9. If the application of the provisions of this act to any wholesale electrical contract existing on the date of its adoption is determined to impair unlawfully any term of such contract or to add material costs to either party, then that contract will be exempt from the terms of this act to the extent necessary to cure such impairment or to avoid the imposition of additional material costs." Effect of Amendment 2019 Act No. 62, SECTION 10, rewrote the section, requiring the Public Service Commission to periodically review the standards for interconnection and parallel operation of generating facilities to an electrical utility's distribution and transmission system. ARTICLE 5 Service Rights of Electric Suppliers

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
South Carolina § 58-27-460, Counsel Stack Legal Research, https://law.counselstack.com/statute/sc/27/58-27-460.