§ 39-33-2. Storage tariff.
No later than September 1, 2024, the public utilities commission shall engage stakeholders
to adopt a framework for an energy storage system tariff for energy storage systems
connected to the electric distribution system.
(1) The tariff framework should, at a minimum, address the ability of energy storage systems
to charge from and discharge to the electric distribution system.
(2) The commission shall set a schedule that is designed to result in a model tariff no
later than May 1, 2025, consistent with the tariff framework.
Free access — add to your briefcase to read the full text and ask questions with AI
§ 39-33-2. Storage tariff.
No later than September 1, 2024, the public utilities commission shall engage stakeholders
to adopt a framework for an energy storage system tariff for energy storage systems
connected to the electric distribution system.
(1) The tariff framework should, at a minimum, address the ability of energy storage systems
to charge from and discharge to the electric distribution system.
(2) The commission shall set a schedule that is designed to result in a model tariff no
later than May 1, 2025, consistent with the tariff framework.
(3) Following that date, if the commission finds that the energy storage system tariff
can be implemented without inequitable cross subsidization between customers, each
electric distribution company as defined in § 39-1-2 that has greater than one hundred thousand (100,000) customers shall file the model
tariff for review and approval by the public utilities commission in a contested proceeding.
Otherwise, the model tariff shall be included as part of the electric distribution
company's next general rate filing.