§ 39-26.3-2. Definitions.

The following terms shall have the meanings given below for purposes of this chapter:

(1) "Applicant� means an electric distribution customer or distributed-generation developer who submits an application to the electric distribution company for the installation of a renewable distributed-generation interconnection to the distribution system for a renewable distributed-generation project that, as contemplated, meets the eligibility requirements for net metering contained within this title or the eligibility requirements for a standard contract contained within this title.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

P.L. 2011, ch. 140, § 1; P.L. 2011, ch. 144, § 1; P.L. 2017, ch. 112, § 1; P.L. 2017, ch. 176, § 1.