§ 24-8-23. Cost of construction or repair of bridges used by public utilities.
(a) Upon the completion of the construction, reparation or reconstruction of any of the
bridges, used by any public utility, the director of transportation shall file a full
and detailed statement setting forth the amount expended in the construction, reparation
or reconstruction of each bridge used by any public utility, with the public utility
administrator, and a copy of the statement shall be filed in the treasurer's office
of the public utility. The public utility administrator, shall immediately set a time
for hearing and shall, after notice of the hearing to
Free access — add to your briefcase to read the full text and ask questions with AI
§ 24-8-23. Cost of construction or repair of bridges used by public utilities.
(a) Upon the completion of the construction, reparation or reconstruction of any of the
bridges, used by any public utility, the director of transportation shall file a full
and detailed statement setting forth the amount expended in the construction, reparation
or reconstruction of each bridge used by any public utility, with the public utility
administrator, and a copy of the statement shall be filed in the treasurer's office
of the public utility. The public utility administrator, shall immediately set a time
for hearing and shall, after notice of the hearing to the public utility and to the
department of transportation, determine what amount, if any, of the expense of the
construction, reparation or reconstruction of the bridge or bridges shall be paid
by the public utility upon the basis and in the manner provided in § 39-2-6.
(b) If any payment, determined to be due from any public utility shall not be paid to
the state within one year from the date of the determination by the public utility
administrator of the amount due from any public utility, the state shall be entitled
to recover the amount due in an action of debt, together with interest from six (6)
months from the date of the determination by the public utility administrator, at
the rate of ten percent (10%) per annum, and upon securing judgment against any public
utility, execution shall issue against the property of the public utility.