Oregon Statutes
§ 87.730 — Expiration of lien for failure to bring timely foreclosure suit
Oregon § 87.730
This text of Oregon § 87.730 (Expiration of lien for failure to bring timely foreclosure suit) is published on Counsel Stack Legal Research, covering Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Or. Rev. Stat. § 87.730 (2026).
Text
A lien created under ORS 87.705 expires unless suit to foreclose the lien is brought in an appropriate court no later than the 45th day after the date final payment to the agricultural producer is originally due or, if the producer extends the lien by filing a notice of lien under ORS 87.710, no later than the 225th day after the date final payment to the producer is originally due.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Legislative History
1973 c.647 §8; 2001 c.301 §14
Nearby Sections
15
Cite This Page — Counsel Stack
Bluebook (online)
Oregon § 87.730, Counsel Stack Legal Research, https://law.counselstack.com/statute/or/87.730.