This text of Oregon § 757.963 (Public utility required to develop wildfire protection plan; rules) is published on Counsel Stack Legal Research, covering Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Or. Rev. Stat. § 757.963 (2026).

Text

(1)A public utility that provides electricity must have and operate in compliance with a risk-based wildfire protection plan that is filed with the Public Utility Commission and has been evaluated by the commission. The plan must be based on reasonable and prudent practices identified through workshops conducted by the commission pursuant to ORS 757.960 and on commission standards adopted by rule. The public utility must design the plan in a manner that seeks to protect public safety, reduce risk to utility customers and promote electrical system resilience to wildfire damage.
(2)A public utility that provides electricity shall regularly update a risk-based wildfire protection plan on a schedule determined by the commission. The plan must, at a minimum:
(a)Identify areas that are subjec

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 757.960
Oregon § 757.960
§ 757.210
Oregon § 757.210

Legislative History

2021 c.592 §3

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Oregon § 757.963, Counsel Stack Legal Research, https://law.counselstack.com/statute/or/757.963.