Oregon Statutes
§ 757.557 — Underground utility facility operators required to subscribe to center; liability for damage from excavation for nonsubscribers; exemption
Oregon § 757.557
This text of Oregon § 757.557 (Underground utility facility operators required to subscribe to center; liability for damage from excavation for nonsubscribers; exemption) is published on Counsel Stack Legal Research, covering Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Or. Rev. Stat. § 757.557 (2026).
Text
(1)Every operator of underground facilities shall subscribe to the Oregon Utility Notification Center.
(2)Any person intending to excavate shall notify the Oregon Utility Notification Center at least two but not more than 10 business days before commencing an excavation. The board of directors shall, by rule, provide an exception to the requirement of advance notice for excavators in cases that involve an immediate danger to life or property, or a customer service outage. The board may adopt additional exceptions as the board, in its discretion, determines necessary.
(3)Nonsubscribing operators of underground facilities shall be responsible to all injured parties for all costs associated with damages to such facilities, loss of product or service or damages that occur as a result of exc
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
1995 c.691 §4; 2001 c.104 §294
Nearby Sections
15
§ 757.005
Definition of public utility§ 757.007
Contract and rate schedule filing for certain furnishers of heat exempt from regulation; procedure§ 757.010
§ 757.010§ 757.025
§ 757.025§ 757.030
§ 757.030§ 757.040
§ 757.040§ 757.045
§ 757.045Cite This Page — Counsel Stack
Bluebook (online)
Oregon § 757.557, Counsel Stack Legal Research, https://law.counselstack.com/statute/or/757.557.