Text

(1)If any person operating a hydroelectric project fails to advise the Water Resources Department within 60 days of the time established in ORS 543A.030 or 543A.075, the Water Resources Commission may order the decommissioning of the project.
(2)The Water Resources Commission shall adopt by rule procedures for ordering a decommissioning of a project and standards for conducting a decommissioning in a manner that ensures the protection of the public health and safety and the environment. The rules shall include a provision for establishing a Hydroelectric Application Review Team for the project to coordinate the activities of all state agencies involved in the decommissioning process.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WaterWatch of Oregon v. Water Resources Dept.
501 P.3d 507 (Oregon Supreme Court, 2021)

Legislative History

1997 c.449 §30